ALIENO video:
09.03.2024
ALIENO. Purpose of the initial mobile halls 1 - 14.
Purpose of the initial mobile halls 1 – 14, which have an area of 2300 square meters in total and allow in the ALIENO factory already to be produced the initial prototypes of the ALIENO hypercars.
29.02.2024
ALIENO. 1 month since the start of production of the initial prototype of ALIENO hypercar.
Ahmed Merchev (founder, CEO and CTO), shows the progress in the first month since the start of the production of the initial full-size prototype of ALIENO electric hypercar, and the execution of the first step according to the order-declaration with which he commissioned its production, namely that the cockpit of the car is already manufactured and he got into it. The prototype will be completed by 24.05.2024 and will be demonstrated then in Slashten, Bulgaria. Additional information and details are available in the order-declaration available at the following address:
Order-declaration number 20240127 from 27.01.2024
29.01.2024
ALIENO. Order-declaration number 20240127 from 27.01.2024. Camera 2of2.
Ahmed Merchev (founder, CEO and CTO), assigns the team to produce an initial full-size prototype of ALIENO electric hypercar by 24.05.2024, i.e. for a period of 4 months, and it to be demonstrated then in Slashten, Bulgaria. The original order-declaration and its full text are available at the following address:
Order-declaration number 20240127 from 27.01.2024
27.01.2024
ALIENO. Order-declaration number 20240127 from 27.01.2024. Camera 1of2.
Ahmed Merchev (founder, CEO and CTO), assigns the team to produce an initial full-size prototype of ALIENO electric hypercar by 24.05.2024, i.e. for a period of 4 months, and it to be demonstrated then in Slashten, Bulgaria. The original order-declaration and its full text are available at the following address:
Order-declaration number 20240127 from 27.01.2024
01.01.2024
ALIENO. A walk on the ALIENO factory area on the first day of 2024.
Walk in the area of the ALIENO factory on 01.01.2024. The initial concreting of 9000 square meters of the area has been completed and the initial 2300 square meters of mobile halls have been built.